MERITS OF COMBINED CYCLE GAS BASED POWER PLANTS
Why Combined Cycle Gas Based Power Plants in place of Coal Based Sub-critical Thermal Plant (500/600 MW)?
§ The coal stock is diminishing fast and it is becoming increasingly difficult to arrange adequate coal for steady operation of the existing Power Plants.
§ Most of the existing old Units are designed for operation with high GCV coal which is very scarce and costly now. As a result, due to non availability of sufficient quality coal, the existing old Units are suffering from huge generation loss as well as financial loss.
§ Inadequate supply of coal from open cast/underground mines. Dearth of adequate washed coal. Supply of bad quality coal with huge ash, stone and boulders.
§ Exorbitant price rise of Indian coal. Restriction for import of coal. Shortage in supply during monsoon.
§ Limitation of transportation of coal by Railways. Shortage of empty wagons.
§ Social threat in acquisition of agricultural land for green field project. It has become practically impossible to acquire land; may it be barren or single crop.
§ Scarcity of consumptive water availability from river/lake/barrage/dam.
§ Difficulty in Fly Ash Management; there is “No Taker” of such huge quantity of Fly Ash.
§ To combat increasingly stringent environmental norms of MOEF over the years during its life.
Advantages of Combined Cycle Gas Based Power Plants
§ Carbon emissions can be drastically reduced to combat ever increasing global warming threat
§ Guaranteed high cycle efficiency in the range of 59% (+) compared to 36% for coal based sub-critical 500/600 MW capacity thermal Units
§ Land requirement is significantly less; 80 acres for 1000 MW which is 1/10th of coal based sub-critical 500/600 MW capacity thermal Units
§ Total Manpower requirement is less; Man-MW ratio at least 50% less i.e. less job opportunity
§ PLF and Availability Factor is very high; 95% and above since forced outage is minimum
§ Consumptive water requirement is 60% less; a boost in favour of water conservation
§ Project cost is 3.5 Crore per MW compared to 5.5 Crore for 500/600 MW coal based Units
§ Carbon Credit Benefit will be available if the CCPP is installed by abandoning old coal based sub-critical Plants like Bandel TPS or installed as a brown field Project at Bakreswar TPP
§ Issuance of NOC by MOEF will be easy since there is no pollution threat from CCPP
§ Gestation period is 30 months for 1000 MW; this is 18 months less compared to coal based sub-critical 500/600 MW capacity thermal Units
§ In case of ICB, number of participating global Bidders will be high which is most unlikely for sub-critical 500/600 MW coal based thermal Units.
COMPARISON OF COMBINED CYCLE GAS BASED UNIT WITH COAL BASED THERMAL UNIT (500 MW CAPACITY - SUB-CRITICAL TECHNOLOGY)
| Sl. No. | PARAMETER | Natural Gas Based Unit | Coal Based Thermal Unit |
| 1 | Efficiency (η %) | 59.4 (Series701 F4) | 36 (500 MW Unit) |
| 2 | Unit Heat Rate | 1448 Kcal/KWh | 2389 Kcal/KWh |
| 3 | Plant Load Factor | 95% | 80% |
| 4 | Availability | 96% | 85% |
| 5 | Reliability | 99% | 90% |
| 6 | Land Requirement for 1000 MW | 80 Acres | 800 Acres |
| 7 | Consumptive Water Requirement for 1000 MW | 1400 M3/Hour | 4000 M3/Hour |
| 8 | Environment Impact | Environment Friendly | High |
| 9 | Man-MW Ratio for 1000 MW | 0.1 | 0.5 |
| 10 | Gestation Period for 1000 MW | 30 Months | 48 Months |
| 11 | Installation Cost/MW | 3.5 Cr. INR | 5.5 Cr. INR |
| 12 | Fixed Cost per KWh (B) | X | Y (Y>X) |
| 13 | Variable Cost i.e. Cost of Fuel | A | B (A>B) |
| 14 | % Escalation on Cost of Fuel | 30% higher | Base |
FUTURE AHEAD (12TH PLAN) WITH GAS BASED PROJECTS
- Gas-based combined cycle power plants have a substantial share of the overall installed capacity in India till 11th Plan (2007-12).
- A good number of gas based combined cycle plants has been envisaged by Ministry of Power for implementation across the country during 12th Plan (2012-17) to address environmental issues.
- Nearly 40 projects are awaiting clearance from Central Electricity Authority, Ministry of Power.
- Ministry of Power is now giving equal importance to set up more and more combined cycle and super/ultra-super critical plants during 12th Plan Period (2012-17) to address adverse environmental effects.
