SAGARDIGHI – A NEW LAUNCHING PLATFORM OF WBPDCL FOR 3x500 MW UNITS
SAGARDIGHI - A NEW LAUNCHING
PLATFORM OF WBPDCL FOR 3x500 MW COAL BASED THERMAL UNITS
Forward:
2x300 MW Coal Based Thermal Units 1 & 2 was conceived long back in March 2004
for implementation by West Bengal
Power Development Corporation Limited in Phase I of Sagardighi Thermal Power
Project. The Main Plant Package (Boiler-Turbine-Generator & Auxiliaries) of
these two 300 MW Units was the first of its kind constructed by a Chinese EPC
Contractor M/s Dongfang Electric Corporation in India. Apart from Main Plant
Package, Coal Handling Plant was constructed by M/s McNally Bharat Engineering
Limited and Water Intake & Plant Water System by M/s Larsen & Toubro
Limited; whereas the Railway infrastructure for transportation of Coal &
Light Diesel Oil was constructed by none other than RITES, the sister concern
of Indian Railways. Further, 400 kV LILO (loop in loop out) line was
constructed, erected and commissioned
with 400 kV Double Circuit Farrakka-Subhasgram high voltage state/regional transmission
line by the nationally famous M/s Power Grid Corporation of India Limited for
evacuation of power from Sagardighi TPP 220/400 kV Switchyard.
Built at a completed capitalized cost of
Rs. 2750 Crores with substantial financial assistance from Power Finance
Corporation, the 1st 300 MW capacity Unit of Sagardighi TPP was
synchronized on December, 2007 followed by the 2nd Unit on July, 2008;
subsequently, the Commercial Operation of the said Units 1 & 2 were declared
by WBPDCL on September, 2008 and November, 2008 respectively for uninterrupted generation
of power.
Both
the Units were dedicated to the Nation by the then Hon’ble Chief Minister in 2008.
During 2009 - 2010 time
span both the 300 MW capacity Units were continually in the bus; the Plant has
achieved its maximum PLF (Plant Load Factor) around 93% in the month August,
2010. Since declaration of COD, the Units are performing satisfactorily with
high Plant Load Factor (PLF); adequate coal supply is the key factor.
Capacity
Addition in 12th Plan: To mitigate
ever rising demand of power in the State, WBPDCL has conceived installation of
higher capacity coal based Units 3 & 4 (2 x 500 MW) at Sagardighi Thermal
Power Project Phase II for implementation during 12th Plan Period
(2012-17) with state of the art technology and better unit heat rate i,e, less
heat input for generation of 1 kWh energy. Accordingly, Development Consultants
Private Limited (DCPL) was appointed as Consultant of the Project. DCPL
prepared the Tender Specifications and then global tender for Main Plant
Package was invited from prospective bidders in the last year for the
installation of 2 x 500 MW Units # 3 & 4 at Sagardighi Phase II. In course
of tender finalization process necessary clearances could be received from
State/Union statutory authorities including WBERC in particular for an atypical
situation like single price bid submitted by BHEL only. Comfort level of WBPDCL
is high as PFC has already granted substantial financial assistance for this 2
x 500 MW Project as requested by WBPDCL. The only one bid of BHEL was opened who
quoted high around 3.9 Crore per MW. Negotiations were held first with BHEL
then collectively with CEA for finalization of the price based on national
level bench mark compared to similar Package with similar scope of work ordered
by other utilities like DVC/NTPC in the past. In the last negotiation meeting
at the chamber of the Chairperson, CEA on January 25, 2011 the price could be
reduced and freeze at 3.22 Crore per MW which was later concurred by WBERC. Ministry
of Power, GoI has granted the Project with Mega Power Project status for
availing “Tax Holiday”. As a result, the completed project cost is likely to be
on lower side. Letter of Awards for Main Plant Package were issued in favour of
BHEL on February, 2011 and they are working on fast pace to achieve agreed
milestones with a target date of Completion of the Project by March, 2015. Of
late, Letter of Awards for Coal Handling Plant Package, Twin Flue Chimney and
Natural Draft Cooling Tower have been placed in favour of renowned and
established Local Contractors like McNally Bharat, Gammon and Paharpur Cooling
Tower respectively through International Competitive Bidding for availing “Tax
Holiday”. Since the Gestation Period of Other Packages are much more less
compared to Main Plant Package, the ordering of balance Packages like Intake
Water & Plant Water System, Ash Handling Plant, Technical Building are
likely to be issued in phases through International Competitive Bidding as per float
in LEVEL-1 Network and it is expected that their completion may be well synchronized
with Main Plant Package lying in the critical path of 48 months.
Phase
- III Project: WBPDCL has
also conceived installation of another 500 MW coal based Unit 5 at Sagardighi
Thermal Power Project for implementation during 12th Plan Period
(2012-17) with state of the art technology and better unit heat rate i,e, less
heat input for generation of 1 kWh energy. Accordingly, Development Consultants
Private Limited (DCPL) has been appointed as Consultant of the Project. DCPL
has already prepared the Draft Detailed Project Report. Necessary actions have
been initiated for obtaining statutory clearances from State/Central Government
Agencies. Environment Impact Assessment (EIA/REIA) Study of Phase - III Unit 5
(1x500 MW) is likely to be taken up soon by WBPDCL. However, mandatory common
facilities for Unit 5, like Coal Handling Plant and Intake Water & Plant
Water System have already been taken up concurrently during the implementation
of Phase - II Units 3 & 4 including interfacing of identified areas of respective
Main Plant Packages of the said two Phases with an objective to retain the
estimated project cost of Unit 5 at a lower side.
Posted by Debabrata Dey on 12 July, 2012

0 Comments:
Post a Comment
Subscribe to Post Comments [Atom]
<< Home